Construction on Meta’s one-gigawatt data centre north of Edmonton has advanced too far for the federal environment minister to designate it for review. The Impact Assessment Agency of Canada said on November 10 that work had “substantially begun,” the cutoff set by the federal Impact Assessment Act.
Meta broke ground on July 8. The agency received a request on September 4 to assess the campus and its proposed gas-fired power plant together. It had already reviewed the Greenlight Electricity Centre separately. Meta expects to invest more than $13 billion in the Sturgeon County campus, its first data centre in Canada. DataCentre.ca